week 10

7/6/2010 - 11/6/2010

1. Mostly help En. Hafiz updated the data at office.
2.Mostly preventive shutdown was held during night .


(8.6.2010)

1.Follow team project off to shutdown at Perindustrian Nusa Cemerlang. This project is to create new supply at the new substation ( P/E Tong Garden )
2. Create loop in and loop out works at the new substation.
3. make a direct connection for incoming and outgoing cable.
4. resistance used to obtain the correct phase sequence. (R=10 ohm , Y= 0 ohm , B= 1 ohm )


























(10.6.2010)

1. Went to Taman Setanggi today because there was three feeder pillar ( fp No.9, No.10, No. 11 ) which have been broken and was stolen. Things that have been stolen was busbar and link unit and cause interference to the customer.
2. Before repair the feeder pillar, the main supply from P/E Taman Setanggi No.3 was off.
3. The total loss for the three feeder pillar is around RM18,000. 4. Learn how to install meter box at Taman Setanggi. the meter was single phase meter.





























4. Off to P/E Taman Damai Jaya, to detect the cause of failure.After checking the fuse and still cannot find the cause of failure, the job was assigned to fault finder team.


5. Around 4 pm, breakdown project at P/E Bayu Puteri No.3. The cause of failure was at the switchgear. The bushing at switchgear got contact with earth and created spark ( heat ) and that make the bushing explode. Generator set was used to gave supply to the customer so that the customer will not affected by the maintainance works.