Today is my second week under SAVR team. Today we went again to Taman Munsyi Ibrahim. Our team have to extend a connection from main to the black box. It was done as a standby system if in case it is over load.
Cable ABC 3x195mm2 have been used for this system. For each cable, one to three, we have to mark the cable using tape referred to the phase of the system. the forth cable is neutral cable. For neutral cable, the diameter is smaller than other cable. The numbering is done to make sure the connection is correct after we cut out the cable. Each cable have their owned number but the number is too small. Thats why, we have to mark it with tape to make things easier for connection purposes. We have to connect the cable correctly to prevent electrical component for house or system that used three phase system from damaged. If it is connect not in order, the electrical equipment such as air conditioner ( or anything that run by motor ) will easily damaged because the motor will rotate anti-clockwise and cause heat. From time to time, the equipment will blow.
Cable ABC 3x195mm2 have been used for this system. For each cable, one to three, we have to mark the cable using tape referred to the phase of the system. the forth cable is neutral cable. For neutral cable, the diameter is smaller than other cable. The numbering is done to make sure the connection is correct after we cut out the cable. Each cable have their owned number but the number is too small. Thats why, we have to mark it with tape to make things easier for connection purposes. We have to connect the cable correctly to prevent electrical component for house or system that used three phase system from damaged. If it is connect not in order, the electrical equipment such as air conditioner ( or anything that run by motor ) will easily damaged because the motor will rotate anti-clockwise and cause heat. From time to time, the equipment will blow.
0 comments:
Post a Comment